and beams are formed by bolting through metal plates, which are protected with anti-corrosion paint to prevent rusting. (Fig. 11)

 

Floors
The floors comprise a 50 mm concrete slab with steel reinforcement set on a permanent formwork of continuous split bamboo beams bearing on timber joists.

 

Ground Floor Walls

At ground level the walls comprise 140x280x80 mm compacted mud bricks, laid in a 1:16 earth-concrete mortar. (Photos 02 and 03)

 

First Floor Walls

Structurally, the walls are made of prefabricated timber panels based on standard modules of 80x700x2200 mm; 80x700x1,800 mm and

linea.gif - 0,16 K

Contents | Preface | Acknowledgements | Abstract | Introduction
Objective | Methodology | Conclusions | Bibliography

Trade-off Methodology for Low-Cost Housing Construction Technologies
Page
14

anterior proxima

| main page |